Previous Page  58 / 112 Next Page
Information
Show Menu
Previous Page 58 / 112 Next Page
Page Background

58

/ BUILDING DIALOGUE / MARCH 2015

SlabTek: a Cost-Effective Alternative to ‘Floating Slabs’

F

loating slabs. Don’t just you love that name?

Let’s design floors that “float.” It just doesn’t

sound right, especially for a structural engi-

neer. But, we all know that when you place a floor

directly on our sensitive Colorado soil, it is going

to move. So we create what we call a floating sys-

tem. Since it is cheaper to use a slab-on-grade for

a commercial floor, we design for the anticipated

movement. The lower-level walls are hung from

the framing above, leaving a gap along the bottom

to allow the slab to move without distressing the wall

(or set the wall on the slab with the gap at the top).

This void system can get complicated in addition to

the plumbing and mechanical systems, which must

be sleeved or made flexible for the slab to move. Store-

front doors also need to be installed in such a way as to

be isolated from the slab to avoid the constant scrape

at the bottom. And, by the way, the floor is still going

to move, so be aware of tile or other rigid-type floor

toppings.

OK, so how expensive can the options be? A struc-

tural floor that spans over the soil is typically the alter-

native. But, just the name sounds expensive! Typically

a wood-framed floor is used, consisting of floor joists

and beams. This requires a crawlspace for the 18-inch

clearance above the soil, per code. The framing and

crawlspace requires a raised-floor level or a deeper ex-

cavation. This space also must be ventilated to control

mold issues. Steel joists can be used to cut down on the

clearance, but now the cost of the structural material

is escalating.

A structural concrete floor can significantly reduce

this depth, since the only clearance needed is a gap to

allow for soil heave. But, conventionally reinforced con-

crete slabs are limited in their span lengths, requiring

additional supporting beams and pier supports. These

supports are in addition to the foundation pier system.

The slabs also must be supported by formwork during

the pour and curing process, which can be expensive.

This brings us to a proven alternative system that

was introduced to Colorado last year: SlabTek. This is

a structural slab system that is poured directly on the

ground and then lifted into place, avoiding the costly

formwork. The slab also utilizes proven post-tension-

ing systems that span directly between isolated piers

without the use of costly deep beams. Piers are laid out

in a grid fashion under the entire footprint, typically

eliminating 20 percent of the piers of a conventional

pier-and-grade beam system. Structurally rated lifting

mechanisms are placed at each pier. Post-tension ca-

bles are laid out in both directions. The slab is poured,

typically 5-inches thick. After a three-day cure, the

John

Clarke, PE

President,

RMG –

Rocky

Mountain

Group

TRENDS

in Floor Construction